Risk analysis and safety measures of eight high risk operations
Safety month period in July, the safety of production work is not sloppy. This paper share the risk analysis and safety measures of eight dangerous work with you, the security Quanqian day, a day more than the accident!
Five, open circuit operation
1, risk analysis: identify unknown, information communication is not smooth, affect traffic, cause accident
Safety measures:
1 before operation, traffic shift lever, the construction unit is arranged in the circuit breaker identification for intersection, traffic tips bypass line.
The traffic control department approval "breaker Operations Certificate", immediately notify the relevant departments such as dispatch.
2, risk analysis: during the operation, no appropriate safety measures or not in place, causing traffic accidents or personnel injury accidents
Safety measures:
In the course of the operation, the construction unit shall be responsible for the fence and traffic warning signs at the construction site, and the red light should be hoisted at night.
In the case of open circuit construction, the construction unit shall set up the safety inspection staff to ensure the smooth flow of the highway in the emergency situation.
In the circuit construction during the operation, the construction unit shall not be arbitrarily heaps of construction materials.
3, risk analysis: after the end of the operation, the scene is not completely clean, impede traffic, can cause accidents
Safety measures:
The circuit breaker after the operation, the construction unit shall be responsible for the cleaning of the scene, the lever, breaker signs, fences, warning signs, warning lights removal of the scene and intersections, the traffic control department report.
The traffic control department to the on-site inspection and verification, notify the circuit work units to the end, to restore traffic.
4, risk analysis: change without approval, cause accident
Safety measures:
The circuit breaker operating circuit breaker operation should be carried out according to "card" content, no alteration, lent "breaker Operations Certificate", it is strictly prohibited to modify work content, expand the scope of work or transfer of working position.
In the "open operation permit" within the time required to complete the operation of the circuit breaker, the application unit to re apply for the circuit.
5, risk analysis: the combination of dangerous operations, the corresponding security measures are not implemented
Safety measures:
If it involves high earth and other dangerous operations, should also apply for work permit.
6, risk analysis: the construction conditions of major changes
Safety measures:
If the construction conditions of major changes, should be re apply for "open circuit".
Six, excavation work
1, risk analysis: pipeline, cable damage, causing accidents
Safety measures:
The power cable has been confirmed, and the protective measures have been implemented.
The telecommunication cable has been confirmed, and the protective measures have been implemented.
The underground water supply and drainage pipeline, process pipeline has been confirmed, the protection measures have been implemented.
The earth near the underground facilities, should be gently mining, prohibit the use of grab machine tools.
It has crossed construction scheme according to the diagram
The road construction work has been reported; transportation, fire control, scheduling, safety supervision and management department
2, risk analysis: the collapse occurred
Safety measures:
The people at the same time digging should keep a safe distance.
The excavation should be from top to bottom, not by digging anchor way, dug out of the earth are not allowed to clog the sewer and manhole.
Excavation without slope ditch, pit and other must be set up support, before excavation, try to exclude surface water, when the underground water level to dig below, it is necessary to take drainage measures.
The slope has been processed and wall support.
The operating personnel must wear a helmet. The upper edge of the pit, the trough, the well and the ditch is not allowed to stand and walk.
3, risk analysis: the emergence of poisoning
Safety measures:
Combustible gas detector, toxic medium detector.
Operators must wear protective equipment.
Personnel import and export and evacuation protection measures have been implemented: A ladder B, repair slope.
4, risk analysis: causing the fall
Safety measures:
Operating site fence, warning line, warning cards, night warning lights have been set according to the requirements.
There is sufficient lighting at night in the work site: A ordinary lamp B explosion-proof lamp.
When the operators to lay a springboard.
5, risk analysis: the combination of dangerous operations, the corresponding security measures are not implemented
Safety measures:
If it involves high, open circuit and other dangerous operations, should be handled at the same time related work permit.
6, risk analysis: the construction conditions of major changes
Safety measures:
If the construction conditions change, should apply for work permit "to" earth.
Seven, lifting operation
1, risk analysis: operation without a license
Safety measures:
Lifting and command personnel must undergo professional training certificates.
2, risk analysis: Command chaos
Safety measures:
Non emergency situations, the scene of a unified command, the signal is clear.
3, risk analysis: no warning line or warning signs
Safety measures:
There is a perfect lifting scheme, designated warning line, set up safety signs, prohibit non construction personnel into the.
4, risk analysis: poor operating conditions
Safety measures:
There should be adequate lighting at night.
In case of heavy rain, fog and strong wind at 6 or more, the operation must be stopped.
5, risk analysis: not strictly enforce the lifting operation “ ten not hanging ”
Safety measures:
Command signal is unknown or arbitrary command not hanging;
Overload or object weight is not unknown;
The heavy load is not hanging;
The lack of light, see the heavy crane;
The station is not under a weight lifting;
The weight is not hanging in the ground;
The fastening weight is not strong, rope knotted rope uneven crane;
The edge objects not put measures without lifting pad;
9 safety device failure is not suspended;
The weight over head crane.
6, risk analysis: the combination of dangerous operations, the corresponding security measures are not implemented
Safety measures:
In the process of lifting the road traffic, such as the need to block the road traffic, should apply for "open circuit".
Lifting the scene, operating personnel board 2 meters above the height of the work, should handle the "height of the work permit".
Related work permits for other hazardous operations.
Eight, blind plate pumping operation
1, risk analysis: the blind plate has a defect
Safety measures:
Blind plate material to be appropriate, the thickness should be calculated by strength, high pressure blind plate should be passed inspection, the blind plate should have a
Two handles, easy to identify, pump, should be used to match the gasket.
2, risk analysis: hazardous substances (energy) outstanding
Safety measures:
Before the dismantling of the blind plate, should bePipe pressure to pressure or micro positive pressure;
Is strictly prohibited in the same pipe at the same time two and two more than the blind plate;
Gas temperature should be less than 60;
The workers are no harmful substances (energy) may highlight the direction for personal protection.
3, risk analysis: fire and other fire
Safety measures:
In the operation of flammable and explosive places, there is not 30m hot work site of operation; lighting use explosion-proof lamps; use explosion-proof tools, prohibited beat pipeline, with iron flange etc..
4, risk analysis: operational mistakes
Safety measures:
When the multiple blind plate is drawn, the position map of the blind plate and the blind plate number shall be in accordance with the unified command of the operation responsible person;
The signs indicate that the blind plate position should be located in each of the blind plate.
5, risk analysis: poor ventilation
Safety measures:
The doors and windows open, to strengthen the natural ventilation;
Partial forced ventilation.
6, risk analysis: improper care
Safety measures:
There should be a special person to monitor the operation, before the end of the job, the guardian shall not leave the job site;
The guardian should be familiar with the site environment and inspection and confirmation of security measures in place, with relevant safety knowledge and emergency skills, and job to maintain contact, at any time to grasp the changes in the conditions.
7, risk analysis: emergency response
Safety measures:
The operation is complex and dangerous places, in addition to the guardian, other relevant departments should be to the scene, prepare for emergency.
8, risk analysis: the combination of dangerous operations, the corresponding security measures are not implemented
Safety measures:
If it involves fire, limited space, high risk operations, should also apply for work permit.
9, risk analysis: the operating conditions of major changes
Safety measures:
If the operating conditions of major changes, should be re apply for "block out of the work of the blind plate".