Project management of 44 time nodes in the project
First, the bidding time

1, the deadline for submission of bids: valid for at least 20 days
2, tender documents: 15 days before the deadline for submission of bid documents
3, surveying the scene: 1-2 days before the tender preparation
4, tender preparation: the tender documents issued after 7-28 days
5, the bidder found the tender documents are in error, within 7 days of receipt of the tender documents in writing
6, refund the bid security: 14 days after the expiration of the validity of the tender, the contract within 5 days after the contract
7, the bank or Guarantee Corporation issued a letter of guarantee, in the effective period after the expiration of the validity of the tender to continue to be effective
8, the tender evaluation should be completed before the end of the 30 working days of the end of the validity period of the tender
9, to determine the winning bidder within 15 days after the submission of the bidding report
10, issue a bid winning notice within 30 days after the signing of the contract
7, 11 days after the conclusion of the contract, the construction of the administrative departments for the record
Two, the duration of the contract performance period

12, the employer to replace the representative, at least 7 days ago to notify the contractor in writing
13, the oral instruction of the engineer, in 48 hours to confirm in writing. The Contractor shall, within 7 days after the oral instruction, make a written confirmation request within days after the written confirmation shall be made within 48 hours. No, no, no, no, no, no, no, no, no, no, no, no, no, no, no, no, no
14, not according to the agreement between the date of the start of construction, the contractor at least 7 days in advance to explain the reason, the Engineer within 48 hours after receipt of an application to a written reply within, not agree with diplopia
14 days, 15 period may extend the situation and report in writing to the Engineer
16, the engineer can not be on time to participate in the acceptance, must be 24 hours before the acceptance of the contractor to put forward an extension of the request, the extension can not be more than 2 days
14. The Contractor shall report to the Engineer within 17 days after the price adjustment.
18, to the payment within 7 days after the date of payment of the contract to the employer to ask for
19, the engineer has received 7 days after the end of the project report to verify, and 24 hours before the verification of the contractor to notify the contractor
20, progress: 14 days after the confirmation of measurement, the contractor to pay the project
21, the developer received 28 days after the completion of the acceptance report within days of acceptance, and within 14 days after the acceptance of recognition
28, within 22 days after the completion of the acceptance report, the Contractor shall submit the completed settlement report and the complete information to the employer, and the employer shall verify and confirm the settlement price within 28 days.
14, the Contractor shall, within 23 days after receipt of the settlement funds, transfer the project to the employer
24, the quality guarantee period of 14 days, the refund of the warranty
Three, change and claim the time

25, change the event occurred within 14 days after the report of the project price change, 7 days to confirm. No reason to confirm, after 14 days from the report to take effect
26, the claim within 28 days after the occurrence of the notice of intent to issue a notice of intent, within 28 days after the submission of the relevant information, engineers reply within 28 days. Did not reply, it is deemed to be recognized. Continuous occurrence of the event, the stage of the claim, within 28 days after the end of the final report submitted to the report
Four, FIDIC under the conditions of the contract

2, the oral instruction of the Engineer shall, within 27 days after receipt of the written confirmation of the contractor, reply to the written instruction from the oral instruction.
28, the replacement of the engineer, the Contractor shall notify the contractor 42 days in advance
29, the Contractor within 28 days after receiving the letter of acceptance to the owners to submit a performance guarantee
21, the owners in 30 days after the receipt of a copy of the warranty certificate, the contract will be returned to the contractor
31, the Contractor within 42 days after receiving the letter of acceptance
32, engineers in the 7 days before the start date issued a notice
28, the Contractor within 33 days after receiving the notice to submit a detailed schedule of Engineers
21, the performance guarantee and the payment of the letter to the engineer, 34 days after the issuance of the notice of payment to the Engineer
35, progress payment: 28 days to receive the payment report issued by the contractor
36, the owner of the payment schedule should not exceed the engineer received the Contractor's monthly progress payment of 56 days after the application
37, the completion of inspection: the contractor 21 days in advance to determine the date of notice of engineers, engineers in the days after the date of 14 days
38, receive a certificate: after the completion of the basic requirements, in the 14 days before the transfer of work can be completed in writing to the Engineer for the issuance of engineering. The Engineer within 28 days after the application.
39, the completion of the settlement: 84 days after the issuance of the receipt of the project contract, the contract for the completion of the report, within 28 days of the visa, payment and settlement
28, within 40 days after the expiration of the notice period, the Engineer shall issue a certificate to the owner of the contractor responsible for the defect of the project, and issue a certificate of compliance. Within 14 days after the certificate, the owner returned the performance guarantee.
41, the final settlement: 56 days after the issuance of the contract, the contractor to submit the settlement statement, the engineer 28 days to sign the payment certificate, within 56 days after receipt of the certificate
42, the engineer of the dispute decision: 84 days to inform the parties to the decision, if 70 days later, the two sides did not pay the notice of arbitration, the decision is final
43, the decision of the Dispute Adjudication Board: within 84 days after receiving the written report to make a decision, if not satisfied, within 28 days of the other party to issue a notice of dissatisfaction, and to draw the arbitration
56, the decision must be made by the decision of the Commission 44 days after the application
Process equipment network finishing release, reproduced please indicate the source.